Tanasi Ground Breaking
Tanasi Update December 2024 Board Meeting
Scott Macrae, Senior Project Manager, reported that the Tanasi Rebuild is in Phase Zero.This phase focuses on safety and erosion control, cart path relocation, and temporary sewer, water, and electrical for the existing pro shop.
Tanasi Update Board Meeting October 2024
Tanasi Contract- Chet Pillsbury & Marty Inkrott Presented Key Points Costs: The contract is not to exceed $9.94M; this includes building, site work,& parking Other costs, including golf green, landscaping, design, furniture & fixtures, kitchen, and others,...
Tanasi Update September Townhall 2024
September Update
At yesterday's board meeting, Board Member Marty Inkrott provided an update on the progress of the Tanasi rebuild project. We are now in the final stages of contract negotiations with RTC, a Knoxville-based company that successfully built the Toqua Clubhouse for us in...
August 2024
The Tanasi Clubhouse rebuild has been through a thorough and detailed process aimed at achieving the best possible result within our budget constraints. Initially, we reached out to nine contractors, and we were pleased to receive responses from four—Taylor the...