Roadwork Schedule
Paving Project Begins August 18, 2025
Harrison Construction will begin milling and paving work on Monday, August 18, 2025. This project will start in the Tanasi Shores Neighborhood, then move to the Mialaquo Neighborhood once Tanasi Shores is complete.
Crews may also perform some pre-paving repairs in Mialaquo before milling begins there. Work is expected to take 5–6 days in Tanasi Shores and 3–4 days in Mialaquo, but weather conditions may affect the schedule.
Traffic & Safety Notes
- Roads will remain open during the project.
- Flaggers will direct traffic, but expect occasional delays.
- Street parking will be prohibited during milling and paving.
- Please drive slowly through work zones for your safety and the safety of the crews.
- If you have scheduled appointments, you might consider allowing extra time.
Planned Paving Schedule
Tanasi Shores Neighborhood
- Erick Lane (projected starting point)
- Mingo Way
- Mingo Drive
- Inola Place
- Nicoma Circle
- Nicoma Drive
- Depew Drive
- Mingo Lane
- Keota Lane
- Keota Place
Mialaquo Neighborhood
- Mialaquo Road
- Portion of Elohi Way (from Elohi Lane intersection to the first Noya Way intersection)
- Nuhya Way
- Nuhya Lane
- Nuhya Trace