Toqua Construction Updates: 6/11/19

The latest: Plywood on the roof is complete. The metal roof is scheduled to be installed in about three weeks. The fire sprinkler system is being installed. HVAC contractor is onsite. Electrical rough-in is underway. The kitchen hood has been installed. Framing...