Tanasi Updates 2025

January 2025 Townhall February 2025  Townhall  April 2025 BOD May 2025 Townhall  June 2025 Townhall  July 2025 Townhall 

Tanasi Update December 2024 Board Meeting

Scott Macrae, Senior Project Manager, reported that the Tanasi Rebuild is in Phase Zero.This phase focuses on safety and erosion control, cart path relocation, and temporary sewer, water, and electrical for the existing pro shop....

Tanasi Update Board Meeting October 2024

Tanasi Contract- Chet Pillsbury & Marty Inkrott Presented Key Points Costs: The contract is not to exceed $9.94M; this includes building, site work,& parking Other costs, including golf green, landscaping, design, furniture & fixtures, kitchen, and others,...

September Update

At yesterday’s board meeting, Board Member Marty Inkrott provided an update on the progress of the Tanasi rebuild project. We are now in the final stages of contract negotiations with RTC, a Knoxville-based company that successfully built the Toqua Clubhouse for...