Jun 27, 2019 | Uncategorized
The following three photos show the patio progress. Dining Area Pro Shop
Jun 26, 2019 | Uncategorized
Windows are installed. Cement board siding.
Jun 26, 2019 | Uncategorized
Sheetrock is up and painting will begin soon.
Jun 11, 2019 | Uncategorized
The latest: The electrical rough continues. Insulation will be installed next week. Sheetrock will follow insulation. Painting will follow the sheetrock. EIFS process: foam has been attached to the Densglass. The windows and glass are in...
Jun 11, 2019 | Uncategorized
The latest: Plywood on the roof is complete. The metal roof is scheduled to be installed in about three weeks. The fire sprinkler system is being installed. HVAC contractor is onsite. Electrical rough-in is underway. The kitchen hood has been installed. Framing...