Apr 10, 2019 | Kahite Community Center Updates
Steel for the columns has been set and framing is in progress. Trusses are scheduled for the end of the week.
Apr 10, 2019 | Toqua Clubhouse Updates
Rough-in plumbing is completed and all columns are poured. The insulation board is being installed on the footer building. Electrical rough-in has begun. Pad preparation will begin Thursday, April 11th.
Apr 5, 2019 | Toqua Clubhouse Updates
Rough-in plumbing is underway and column footers are being completed. The fire sprinkler line is tied in, tested, and approved.
Apr 5, 2019 | Kahite Community Center Updates
The building is beginning to take shape with framing and columns.