Mar 8, 2019 | Uncategorized
We are glad to have had a few days of good weather. Below are some of the highlights that took place this week.
Mar 6, 2019 | Uncategorized
Building layout for footer and columns is complete and they have begun digging columns. The goal is to pour footers and columns by Friday before the next rain.
Mar 6, 2019 | Uncategorized
Construction on the new Toqua Clubhouse is about 2 weeks behind schedule due to heavy rainfall. Additionally, construction crews hit a snag when they discovered a primary direct line buried under the left front corner and under the front columns. Loudon Utility Board...