Mar 27, 2019 | Uncategorized
Column footers Plumbing Rough-in
Mar 27, 2019 | Uncategorized
On Tuesday March 26th, workers poured the slab. Lumber will be delivered the 27th, and framers are scheduled to begin March 28th.
Mar 27, 2019 | Uncategorized
Click for photos and the updated construction schedule: https://www.tellicovillagepoa.org/wp-content/uploads/2019/03/ToquaUpdate-3-20-19.pdf
Mar 27, 2019 | Uncategorized
Click for photos and the updated construction schedule: https://www.tellicovillagepoa.org/wp-content/uploads/2019/03/KahiteUpdate-3-20-19.pdf