The latest:
- Plywood on the roof is complete.
- The metal roof is scheduled to be installed in about three weeks.
- The fire sprinkler system is being installed.
- HVAC contractor is onsite.
- Electrical rough-in is underway.
The kitchen hood has been installed.
Framing continues. Shown above is the restaurant bar.
Ductwork is being staged.